TCF Design and Engineering: Drawings and Deliverables Explained

BoldTarget TCF project: camp buildings, electrical distribution cabinet and paved walkway

Temporary does not mean unengineered. A labour camp may house hundreds of people through several Saudi summers, a site office complex may host the owner, the consultant and the contractor for years, and both must withstand wind, sand, heat and heavy daily use. Good TCF design and engineering is what turns a collection of cabins into safe, compliant and efficient facilities. This guide walks through the design deliverables a professional TCF package should include, from the design basis and master plan to architectural, structural and MEP drawings, shop drawings and as-builts, and explains what clients should check at each stage.

Start with a clear design basis

Every good TCF design starts with a short document that fixes the inputs. Without it, the design changes every time someone gives a new headcount. A design basis normally records:

  • Population and phasing: peak and average headcount for staff and labour, and how it changes over the project.
  • Duration: expected service life, which affects material choices and reuse planning.
  • Site data: topographic survey, soil information, access, flood risk and neighbouring activities.
  • Utilities: availability of grid power, water and sewer, or the need for generators, tankers and treatment plants.
  • Standards: Saudi Building Code, Civil Defense expectations, labour accommodation standards and any owner specifications.
  • Climate: design temperatures, prevailing wind direction, dust exposure and, on coastal sites, humidity and corrosion.

Our pre-construction services help clients agree the design basis before any drawing is started, which is the cheapest moment to make decisions.

Master plan and site layout

The master plan sets the zones: offices, accommodation, kitchen and dining, welfare, workshops, laydown, parking, utilities and waste areas. Key engineering decisions at this stage include separation distances for fire safety, placing generators and kitchens downwind of accommodation, keeping heavy traffic away from pedestrian routes, emergency vehicle access, drainage falls and space for expansion. Our article on construction site layout planning for TCF covers zoning principles in detail.

Architectural design

Architectural drawings turn the master plan into usable buildings. They cover floor plans, room layouts, elevations, door and window schedules, finishes and furniture layouts. For accommodation, the drawings must demonstrate compliance with room space, ventilation, natural light and sanitary provisions required by labour accommodation standards and the owner. For offices, they address meeting rooms, document control, server rooms, prayer areas and visitor reception. Accessibility, shading, entrances and covered walkways matter more than many clients expect, especially in summer heat.

Structural design for wind, sand and heat

Structural engineering for temporary buildings is often underestimated. Desert and coastal sites in Saudi Arabia expose buildings to strong winds, sandstorms and high temperatures, and stacked or multi-storey cabins add further loads. The structural package should include:

  • Wind load analysis according to the Saudi Building Code and the site exposure.
  • Foundation design based on soil information, whether strip footings, pads, precast blocks or skids.
  • Anchoring and tie-down details for cabins and roof sheets.
  • Stacking, staircase and walkway design for two-storey arrangements.
  • Roof loads for AC units, water tanks and solar panels where used.
  • Connection details that allow future dismantling.

Where light steel framing is used, our light steel framing design and build capability covers frame design, panel layouts and connection detailing in-house.

MEP design: the heart of a working camp

Most performance problems in temporary facilities trace back to MEP design that was too thin or done too late. A complete MEP package typically includes:

Electrical

A load schedule for every building, a single-line diagram, generator or utility connection sizing, cable routes, distribution board schedules, earthing and lightning protection, lighting layouts and external lighting. An accurate load schedule is essential: undersized power is one of the most common and expensive TCF failures. Our electrical engineering team prepares these calculations as part of the design.

HVAC

Heat load calculations for each room type based on Saudi summer conditions, equipment selection, fresh air and exhaust for toilets and kitchens, and condensate drainage routes.

Plumbing and drainage

Water demand and storage calculations, pump and water heater selection, pipe sizing, drainage layouts with falls, grease traps, septic tank or treatment plant design and stormwater drainage.

Fire and low current

Fire alarm and detection layouts, extinguisher and hose reel positions, emergency lighting, and low-current systems such as CCTV, access control, data networks and public address.

Because BoldTarget runs MEP contracting in-house, the same engineers who design these systems coordinate their installation, which reduces clashes and late changes.

TCF design deliverables at a glance

DeliverablePurposeTypical stage
Design basis reportFixes population, duration, site data, standards and climate inputsConcept
Master plan and zoning drawingLocates every facility, road, utility and separation distanceConcept and approval
Architectural drawingsPlans, elevations, room layouts, finishes and schedulesApproval and construction
Structural drawings and calculationsFoundations, wind and anchoring, stacking and connectionsApproval and construction
Electrical load schedule and single-line diagramSizes generators, utility connection and distributionApproval and construction
HVAC heat load calculations and layoutsSelects cooling equipment and ventilationApproval and construction
Plumbing, drainage and sewage drawingsWater storage, distribution, drainage and treatmentApproval and construction
Fire safety and low-current drawingsFire alarm, fire fighting, CCTV, access control and networksApproval and construction
Shop drawingsManufacturing and installation details for each systemBefore fabrication
As-built drawingsRecord of what was actually installedHandover

Shop drawings, coordination and as-builts

Once design drawings are approved, shop drawings translate them into manufacturing and installation details: module dimensions, panel layouts, penetrations, cable trays and pipe routes. A coordinated model or combined services drawing helps catch clashes between structure, ducts, pipes and cable routes before they appear on site. Shop drawings also feed the method statements and inspection and test plans described in our guide to TCF method statements and ITPs.

At handover, as-built drawings record what was actually installed. They are essential for operation and maintenance, for future expansion and for relocating buildings at demobilization, yet they are often the first deliverable to be forgotten.

Design review and approvals

The design package passes through owner and consultant review, and parts of it through authorities such as the municipality and Civil Defense. A clear drawing register, consistent revision control and a response log for every comment keep reviews moving. Our article on TCF permits and approvals in Saudi Arabia explains who reviews what and in which order.

What clients should check before approving a TCF design:

  1. The design basis matches the latest headcount and programme.
  2. Fire separation and emergency access are shown clearly on the master plan.
  3. The electrical load schedule includes all buildings, kitchens and future expansion.
  4. HVAC sizing reflects real summer conditions, not generic assumptions.
  5. Drainage and sewage solutions are realistic for the site.
  6. Structural calculations address wind, anchoring and stacking.

Engineer your TCF properly with BoldTarget

As a TCF contractor in Saudi Arabia with in-house design and MEP capability, BoldTarget delivers the full engineering package and then builds what it designs. Our temporary construction facility project in Saudi Arabia reflects this integrated approach. To discuss the design of your site offices, labour camp or complete TCF, contact BoldTarget and our engineering team will review your requirements.

Frequently Asked Questions

What does TCF design and engineering include?

It typically includes a design basis, master plan, architectural drawings, structural calculations and drawings, MEP design covering electrical, HVAC, plumbing, drainage, fire and low-current systems, shop drawings and as-built drawings. Together these define what will be built, how it will perform and how it will be approved.

Do temporary buildings need structural calculations?

Yes. Temporary buildings in Saudi Arabia are exposed to strong winds, sandstorms and heat, and stacked cabins carry additional loads. Structural calculations for foundations, wind loads, anchoring and stacking are normally required by consultants and owners, and they protect people living and working in the facilities.

Why is the electrical load schedule so important for a TCF?

The load schedule determines generator sizes, the utility connection application, cable sizes and distribution boards. If it is underestimated, the camp may suffer overloads and outages, especially in summer when cooling demand peaks. Including kitchens, workshops and future expansion avoids costly upgrades later.

What are as-built drawings and why do they matter for TCF?

As-built drawings record what was actually installed, including any changes made on site. They are needed for operation and maintenance, for adding new buildings during the project and for dismantling and relocating facilities at demobilization.