TCF Checklist for Project Managers: Planning to Demobilization

BoldTarget TCF project in Saudi Arabia: camp accommodation blocks along a paved internal road

Temporary construction facilities involve dozens of decisions made under time pressure, and a single missed item, such as an undersized generator, an unapproved layout or a forgotten grease trap, can affect the whole project. This TCF checklist brings the critical items together in one place, grouped by phase from early planning to demobilization. It is written for project managers, construction managers and procurement engineers in Saudi Arabia who need to confirm that nothing has been overlooked. Use it at kick-off, at each design review and before occupation, and adapt it to your own owner and project requirements.

1. Planning and requirements

Most TCF problems start with unclear requirements. Fix these inputs before asking anyone for a price.

Check itemWhat to confirm
Headcount and phasingPeak and average numbers for staff, labour and visitors, with the build-up profile
DurationExpected service life and possible extensions
Owner standardsOwner specifications for camps, offices, welfare and HSE
Site dataSurvey, soil information, access, flood risk and neighbouring hazards
UtilitiesAvailability of grid power, water and sewer, or interim solutions
Budget and ownershipBuy, rent or lease decision and end-of-project ownership

2. Procurement and contract

A clear tender package attracts comparable bids. Our guide to writing a TCF tender and RFQ covers this phase in depth.

Check itemWhat to confirm
Scope matrixWho provides design, buildings, civil works, MEP, utilities, furniture, O&M and demobilization
SpecificationsInsulation, finishes, HVAC, fire safety and furniture standards stated clearly
Contractor capabilityIn-house design and MEP, HSE record, relevant references and resources
ProgrammeRequired handover dates by phase, aligned with mobilization
Commercial termsPayment basis, rental terms, buy-back and variation pricing
InterfacesLinks with the main contractor, catering, security and transport providers

3. Design and approvals

Check itemWhat to confirm
Design basisApproved by owner and consultant before detailed design
Master planZoning, fire separation, emergency access, wind direction and expansion space
Structural designWind loads, foundations, anchoring and stacking calculated
Electrical load scheduleAll buildings, kitchens, workshops and future loads included
HVAC sizingBased on real summer conditions and room use
Drainage and sewageRealistic solution for the site: network, septic or treatment plant
Approvals planOwner, consultant, municipality or zone authority, Civil Defense and utilities identified

Our pre-construction services help prepare the design basis and submissions, and our article on TCF permits and approvals in Saudi Arabia explains the approval sequence.

4. Site preparation and civil works

Check itemWhat to confirm
Earthworks and levelsSite graded with falls away from buildings
FoundationsBuilt to approved drawings, levels checked before delivery
Roads and parkingAccess roads, bus bays, parking and dust control in place
StormwaterDrainage channels and soakaways or outfalls functioning
Fencing and gatesPerimeter fencing, gatehouses and controlled entrances

5. Buildings and installation

Check itemWhat to confirm
Factory inspectionUnits inspected before dispatch against approved drawings
Delivery and liftingLifting plans, certified equipment and safe offloading
Weather-tightnessRoof joints, sealants, doors and windows sealed against dust and rain
InsulationWall and roof insulation to specification, no gaps
Finishes and furnitureFlooring, ceilings, beds, lockers and office furniture complete

6. MEP and utilities

MEP is where most failures happen after occupation. With in-house MEP contracting, BoldTarget designs, installs and tests these systems under one team.

Check itemWhat to confirm
Power supplyGenerators or utility connection sized to the load schedule, with backup
Electrical distributionBoards labelled, earthing tested, RCD protection provided
HVACAll units commissioned, condensate drained, kitchen exhaust working
WaterStorage tanks cleaned and disinfected, pumps and heaters tested
Drainage and sewagePipes pressure or flow tested, grease traps installed, septic or STP commissioned
Low currentCCTV, access control, Wi-Fi and data networks working

For security and communications systems, see our low-current systems services.

7. Fire safety, HSE and security

Check itemWhat to confirm
Fire alarm and detectionTested and covering all buildings, including kitchens and stores
Fire fighting equipmentExtinguishers, hose reels or hydrants positioned and tagged
Means of escapeExits clear, emergency lighting and signage working
Fuel and LPG storageLocated and protected according to the approved design
Emergency planAssembly points, evacuation routes and drill schedule
Welfare and HSEFirst aid, heat-stress measures, signage and site rules

Our fire fighting systems team and our HSE approach support this stage.

8. Testing, handover and occupation

Check itemWhat to confirm
Testing and commissioningResults recorded for every system
InspectionsOwner, consultant and Civil Defense inspections completed
Snag listJoint snag list issued and closed
Handover documentsAs-built drawings, O&M manuals, warranties and test certificates
TrainingClient and camp staff trained on systems and emergency procedures

9. Operation and maintenance

Check itemWhat to confirm
O&M scopeHard and soft services clearly allocated
PPM planSchedule for HVAC, generators, water, sewage and fire systems
Help deskFault reporting, ticketing and response priorities
KPIs and SLAAgreed targets and monthly reporting
Waste and hygieneSegregation, licensed haulers, cleaning and pest control

Our guide to camp O&M and facility management explains how to set up this phase.

10. Demobilization

Check itemWhat to confirm
Exit planSequence agreed so facilities close as the workforce reduces
Utility disconnectionSafe isolation and closure of utility accounts
Reuse or disposalUnits for buy-back, transfer, resale or disposal identified
Waste removalTanks emptied and waste removed by licensed providers
Site restorationFoundations removed, site cleaned and handed back

For a deeper look at this final phase, read our guide to TCF mobilization and demobilization planning.

The items most often missed

Across temporary facilities, the same few items are overlooked again and again. Give them extra attention at every review:

  1. Electrical capacity for summer peak cooling and future expansion.
  2. Space in the master plan for additional blocks if headcount grows.
  3. Grease traps, kitchen exhaust and fire protection in catering areas.
  4. Shaded walkways, rest areas and drinking water points for heat-stress protection.
  5. Ablution and prayer facilities sized for the actual workforce.
  6. Stormwater drainage, which seems unnecessary until one heavy rain floods the camp.
  7. Interim power, water and sewage arrangements while utility connections are pending.
  8. As-built drawings and asset registers, essential for O&M and relocation.
  9. Clear responsibility for each item between the client, the main contractor and the TCF contractor.

How to use this checklist

  • Assign an owner and a target date to every line.
  • Review it at kick-off, design approval, pre-occupation and pre-demobilization.
  • Add owner-specific requirements as extra rows.
  • Keep evidence, such as approvals, test reports and photos, linked to each item.

Turn this TCF checklist into a delivered project

As a TCF contractor in Saudi Arabia with in-house MEP and general contracting, BoldTarget can take responsibility for every line of this checklist, from design and approvals to O&M and demobilization. See how we approached our temporary construction facility project in Saudi Arabia, then contact BoldTarget to plan your site offices, labour accommodation or complete TCF.

Frequently Asked Questions

What should a TCF checklist include?

A complete TCF checklist covers planning inputs, procurement and contract, design and approvals, site preparation, buildings, MEP and utilities, fire safety and HSE, testing and handover, operation and maintenance, and demobilization. Grouping items by phase makes it easier to review at each project milestone.

When should project managers use a TCF checklist?

Use it at project kick-off to define requirements, at each design review, before occupation and before demobilization. Reviewing it at these milestones helps catch gaps such as missing approvals, undersized power or unclear scope before they become costly.

Who is responsible for completing the TCF checklist?

The client's project manager normally owns the checklist, but many items are delivered by the TCF contractor, the consultant and other providers. Assigning a responsible party and target date to each line makes accountability clear.

Can one contractor cover the whole TCF checklist?

Yes, a TCF contractor with in-house design, MEP and general contracting capability can deliver most items, from design and approvals to installation, O&M and demobilization. This reduces interfaces compared with using separate suppliers for buildings, utilities and services.