TCF Contractor Scope of Work: Every Package Explained

BoldTarget TCF project in Saudi Arabia: camp accommodation blocks along a paved internal road

When a project team asks for temporary facilities, most people picture a row of cabins. In practice, the TCF contractor scope of work covers far more: site investigation, design, approvals, buildings, power, water, drainage, HVAC, fire safety, roads, fencing, operation and, at the end, removal of everything. Most disputes on temporary construction facilities in Saudi Arabia do not come from poor buildings. They come from scope that nobody wrote down. This guide breaks the scope into clear packages, explains what each one should include, and closes with a client-versus-contractor responsibility matrix you can adapt for your own tender.

Why a Clear TCF Scope of Work Matters

Temporary facilities are usually the first thing built on site and the last thing removed. They sit on the critical path of mobilization: until offices are powered, cooled and connected, the project management team cannot move in, and until labour accommodation is approved, the workforce cannot arrive. A vague scope creates three predictable problems:

  • Gaps – items that both parties assume the other is providing, such as the main power connection, sewage disposal or Civil Defense submissions.
  • Overlaps – items priced twice, for example earthworks included by both the civil contractor and the TCF contractor.
  • Variations – late additions such as extra meeting rooms or a larger mess hall, which cost more because design and procurement are already fixed.

A full-scope TCF contractor in Saudi Arabia reduces these risks by taking responsibility for the complete package and its interfaces, rather than only supplying buildings.

Package 1: Survey, Design and Engineering

The scope starts long before anything is manufactured. A competent contractor should deliver:

  • A topographic survey and site visit report covering access, existing services and flood-prone areas.
  • A master plan that zones offices, accommodation, welfare, workshops, laydown and parking, with fire separation and space for future expansion.
  • Architectural layouts for each building type, with room data sheets and furniture schedules.
  • Structural design for buildings and foundations, considering wind loads and sand accumulation.
  • MEP design: electrical load schedule, single line diagram, HVAC heat-load calculations, water demand, drainage and fire-fighting layouts.
  • Shop drawings, material submittals and, at the end, as-built drawings.

This is where pre-construction and design services pay off. Decisions made at master-plan stage determine cost, approval speed and how easily the facilities can be relocated or expanded later.

Package 2: Approvals and Permits

Responsibility for approvals must be stated explicitly. Typical items include the owner and consultant review of the TCF layout, municipality (Baladiya) requirements where they apply, Civil Defense fire-safety expectations, and applications for utility connections. In many contracts the client or main contractor holds the land permits while the TCF contractor prepares the technical submissions. Write down who prepares each document, who submits it, who attends inspections and who pays the fees. Approval time also belongs in the schedule, not in an assumption.

Package 3: Civil and Site Works

Buildings need a prepared, drained and accessible site. The civil package typically covers:

  • Site clearance, grading, compaction and soil replacement where the soil report requires it.
  • Foundations: concrete strip footings, pads, or steel and precast supports, chosen according to building type and reuse plans.
  • Internal roads, walkways, parking and bus bays, with dust control.
  • Storm-water drainage, which is often overlooked on desert sites until the first heavy rain.
  • Perimeter fencing, hoarding, gates and guard houses.
  • Shade structures, smoking areas and outdoor rest areas for workers.

Package 4: Buildings and Fit-Out

This is the visible part of the scope: site offices, meeting rooms, labour and staff accommodation, mess halls and kitchens, washrooms and ablution units, prayer rooms, clinics, stores and security buildings. The scope should specify the building system (porta cabins, modular units, light steel framing or pre-engineered steel), wall and roof insulation, internal finishes, doors and windows, furniture and fixtures. Saudi heat makes insulation and roof design a performance issue rather than a cosmetic one: a poorly insulated building needs larger HVAC capacity and more power for its whole life on site.

Package 5: Utilities and MEP Systems

MEP is where temporary facilities succeed or fail, and where cabin suppliers usually stop. A complete scope includes:

  • Power: temporary generators or a utility connection, synchronising panels, distribution boards, cabling, earthing and external lighting, delivered through our electrical contracting services.
  • HVAC: split units, packaged units or VRF systems sized for summer peaks, plus kitchen exhaust and toilet extraction.
  • Water: storage tanks, pumps, treatment where needed, hot water and distribution networks, handled by our plumbing and drainage team.
  • Drainage and sewage: gravity networks, septic or holding tanks, or a packaged sewage treatment plant.
  • Fire safety: fire alarm, extinguishers, hose reels, hydrants and separation distances, designed with our fire fighting systems specialists.
  • Low current: data networks, Wi-Fi, CCTV, access control and public address.
  • Optional solar PV to reduce generator fuel and run hours.

Because BoldTarget delivers these systems through its in-house MEP contracting division, the buildings and the services behind them are designed, installed and tested by one team, with one point of responsibility when something does not work.

Package 6: Testing, Commissioning and Handover

Handover is not the day the last cabin arrives. It requires insulation resistance and earthing tests, generator load tests, HVAC performance checks, pressure tests on water and fire lines, fire alarm cause-and-effect tests, a joint snag inspection and a handover dossier containing as-built drawings, O&M manuals, warranties and spare-part lists. Defining these steps in the scope prevents arguments about when the facility is actually complete and when the maintenance period begins.

Package 7: Operation, Maintenance and Demobilization

Many projects run their temporary facilities for years, so decide early whether the contractor will provide operation and maintenance: preventive maintenance of HVAC and generators, fuel management, coordination of water and sewage tankers, cleaning, pest control and minor repairs, with response times agreed in a service level agreement. At the end of the project, demobilization covers disconnection, dismantling, transport, site reinstatement and, where agreed, buy-back or relocation of buildings to the next site. Our guide to TCF mobilization and demobilization planning explains how to plan this from day one.

TCF Scope Matrix: Client vs Contractor Responsibilities

Use the matrix below as a starting point. Every project is different, but every line should end up with exactly one owner.

Scope itemTypically client / main contractorTypically TCF contractorPoints to agree
Land, site boundary and access rightsYes–Survey data and setting-out points
Master plan and building designReview and approveYesNumber of design revisions included
Owner and consultant approvalsSubmit and follow upPrepare documentsReview periods in the schedule
Municipality and Civil Defense requirementsPermit holderTechnical drawings and complianceFees and inspection attendance
Earthworks and gradingSometimesUsuallyAvoid double pricing with civil works
Foundations–YesBased on soil report
Buildings, furniture and fit-out–YesFurniture schedule per room type
Grid or water network connectionUtility applicationInternal networks and connection worksExact point of connection
Generators and fuelFuel supply (often)Supply, install, maintainFuel responsibility is a common dispute
Sewage disposalDisposal permitsNetwork, tanks or STPTanker emptying frequency
Fire safety systemsDrills and site rulesDesign, supply, install, testTraining of camp staff
IT, internet and CCTVInternet subscriptionCabling, Wi-Fi, CCTVOwnership of active equipment
Operation and maintenanceOptionalOptionalSLA, KPIs and staffing
Demobilization and reinstatement–YesBuy-back or relocation terms

How to Turn the Scope into a Tender-Ready Document

  1. List every facility with quantities, capacities and the number of occupants.
  2. Attach a master plan, even if it is only a concept sketch.
  3. State the design standards and owner specifications that apply.
  4. Define each utility point of connection and who supplies fuel, water and power until permanent connections exist.
  5. Include the rental or operating duration, extension terms and O&M requirements.
  6. Ask every bidder to complete a scope matrix like the one above, line by line, so offers can be compared fairly.

Our article on writing a TCF RFQ and evaluating bids goes deeper into this step, and the comparison of a TCF contractor vs a porta cabin supplier shows which packages a supplier usually leaves out.

Get a Complete TCF Scope from One Accountable Contractor

BoldTarget combines general contracting, building systems and in-house MEP, so the full scope, from survey and design to handover, maintenance and demobilization, sits with one accountable team based in Al Khobar and working across the Kingdom. See how we delivered our temporary construction facility project in Saudi Arabia, then contact BoldTarget to review your scope matrix or request a proposal for your next site.

Frequently Asked Questions

What is included in a TCF contractor scope of work?

A full TCF scope normally covers survey and design, approvals support, civil and site works, buildings and fit-out, power, HVAC, water, drainage, fire safety and low current systems, testing and handover. Many contracts also include operation and maintenance during the project and demobilization at the end. The exact split should be agreed in a responsibility matrix.

Who is responsible for utility connections on a TCF project?

Usually the client or main contractor applies to the utility provider, while the TCF contractor designs and builds the internal networks and the connection works up to an agreed point of connection. Until permanent connections are available, the contract must state who supplies generators, fuel and water. Leaving this undefined is one of the most common sources of disputes.

Should operation and maintenance be part of the TCF scope?

On projects where facilities stay in use for a long period, including O&M in the same contract keeps responsibility for HVAC, power and water systems with the team that installed them. It should be priced separately with a clear service level agreement and KPIs. Smaller or short projects sometimes keep maintenance in-house.

How do I avoid scope gaps when tendering temporary facilities?

Issue a facility list with quantities, a concept master plan, the applicable specifications and a line-by-line scope matrix that bidders must complete. Define points of connection for every utility and state who handles approvals and fees. This makes bids comparable and exposes missing items before award.